Indexed by:
Abstract:
为解决木寨岭隧道的高应力软岩大变形的施工难题,对现场三台阶法施工进行了数值模拟。分析了开挖后的围岩变形特征及围岩应力状态。研究结果表明:围岩变形以预收敛变形为主,掌子面变形较大。施工过程中,加大围岩超前支护,控制掌子面变形和围岩预收敛变形的发生。该结果可为类似软岩大变形隧道施工提供借鉴。
Keyword:
Reprint 's Address:
Email:
Version:
Source :
交通科学与工程
ISSN: 1674-599X
CN: 43-1494/U
Year: 2020
Issue: 4
Volume: 36
Page: 81-87
Cited Count:
SCOPUS Cited Count:
ESI Highly Cited Papers on the List: 0 Unfold All
WanFang Cited Count:
Chinese Cited Count: -1
30 Days PV: 5
Affiliated Colleges: